Downloads
Overview Search Downloads Submit file Up
Category: Orders
Order by: Default | Name | Date | Hits | [Descending]
Orders Files: 1327
Orders of Kerala Electricity Ombudsman  in pdf format
Files:
P-037-2022-Union Match Works, Kottayam-Order 27-07-2022

Download 
Download

Even though the factory was not functioning, it was not in locked condition. But the regular bill for 05/2021 was issued showing the meter reading status door locked. The Licensee has not replaced the faulty meter within the time limit as per regulation. The meter was replaced only on 11-06-2021. The appellant filed a petition before CGRF, Southern Region, and the Forum in its order dated 16.03.2022 ordered to revise the bill for 06/2021 by taking the proportionate average consumption up to the date of replacement of faulty meter, based on this recalculated average of 238 units and the revised bill has been issued. Aggrieved by the decision of the Forum, the appellant filed the appeal petition and this Authority decides as follow: (10) The electricity bills of May 2021 and June 2021 raised by the Licensee is quashed. (11) The bill raised for the month of May 2021 and June 2021 are to be revised by eliminating the energy charges and energy duty for a period from 14-05-2021 to 11-06-2021. (12) The order of CGRF, Southern Region in OP No.72/2021 dated 16-03-2021 is set aside. (13) Licensee has to issue strict instruction to all concerned officials to strictly abide the Regulations applicable from time to time.
P-031-2022-Smt. Mini Felix, Ernakulamn-Order 25-07-2022

Download 
Download

The appellant installed a grid connected solar system on getting the approval from the Licensee by an approved service provider. On 25-10-2021, the Licensee demanded for Rs.3,540/- as connecting charge and the same has been paid and the solar plant identification number was allotted by KSEBL. The application for meter testing & inspection was submitted on 01-11-2021. The testing was done on 15-12-2021 and solar plant was connected to the grid. As per the appellant, there was a delay of 44 days from the date of application and hence, suffered loss of energy. Appellant’s request is to compensate the loss. The appellant filed a petition before CGRF, Central Region and the Forum dismissed the petition. Aggrieved by the decision of the Forum, the appellant filed the appeal petition and this Authority decides as follow. (14) The Licensee has to reimburse the energy charges for 22 days (from 23-11-2021 to 15-12-2021) collected from the appellant. (15) The order of CGRF, Central Region in OP No.74/2021-22 dated 23-03-2022 is set aside.
P-035-2022-Sri. Ramnath, TVM-Order 20-07-2022

Download 
Download

The High-Tension facilities in the building including the metering facilities were installed by the appellant as per the approval of Kerala State Electrical Inspectorate. The 11 kV feeder from the 110 kV Substation is connected to a 5 panel (HT panel) board in which one is a spare panel. Two feeders are connected to Transformer 1 & 2, which is general load provided by the Licensee. Two feeders are connected to Transformers 3 & 4. Transformer capacity is 1600 kVA each. The outgoing of these transformers is fed to the load through an LT panel., which is having three incoming breakers and two bus couplers. Two sets of Current Transformers of 100/5 connected to the 11 kV feeders of Transformer 3 & 4. These CTs were connected to a summation CT with ratio (5+5)/5 and the summation CT is connected to the ToD meter for recording the energy consumption. The Multiplication Factor would have been = 100 x (5+5) = 40 5 5 On 30-07-2016, an inspection was carried out by the Licensee based on the input received during the energy audit. It is mentioned in the report that a single ToD meter was connected for recording a consumption through two sets of 100/5 CTs and a supporting CT of (5+5)/5. The electrical charges for the common area utilities like HVAC, Lifts etc. was billed to M/s. Carnival Technopark and for this 2 x 1600 kVA transformers are provided by the appellant. The Multiplication Factor used for billing was 20 prior to conducting energy audit instead of the actual Multiplication Factor of 40. There was an underbilling of Rs.6.80 Crores for a period from October 2009 to June 2016. The Licensee issued the bill to the appellant, aggrieved by this, the appellant approached the Consumer Grievance Redressal Forum (CGRF), Technopark, Thiruvananthapuram of the Licensee and the CGRF ordered vide OP No. 1/2019 dated 18-03-2022 that the appellant is bound to pay the short assessment bill issued by the Licensee. Aggrieved by the decision of the Forum, the appellant filed the appeal petition and the Authority decides as follow: (1) The appellant is liable to pay the short assessment bill amount. (2) The respondent shall grant suitable numbers of monthly instalments without interest to pay the short assessment bill by the appellant to the Licensee. (3) The order of CGRF, Technopark, Thiruvananthapuram in OP No.1/2019 dated 18-03-2022 is modified to this extent. (4) The Licensee has to device a proper and rugged system to ensure that the meters and CTs are connected properly and the correct CT ratio has been considered for billing and also ensure that the periodical inspection and testing of meters as specified in the Kerala Electricity Supply Code 2014 is meticulously followed. (5) The Licensee has to device a system to follow the Regulations of KSERC and Regulations of the Kerala Electricity Supply Code 2014 and all applicable regulations.

Contact Us

KERALA ELECTRICITY OMBUDSMAN
D.H. Road & Foreshore Road Junction,
Near Gandhi Square,
Ernakulam, Kerala-682 016
Ph: 0484 2346488, Mob: 8714356488

Any Queries?

Send an email to info@keralaeo.org

Do you Know?

Consumers should submit  petitions to CGRF first before appealing Ombudsman.

Visitors Counter

mod_vvisit_counterToday1571
mod_vvisit_counterAll6214914